Public Works Construction

Construction in Peel: Mississauga

Watermain Replacement and Improvement
Elmbank Road from Viscount Road to Indian Line
Project 18-1311

What are we doing?

  • Replacing and improving the aging watermain along Elmbank Road as shown on the attached map.
  • Replacing the water service pipe to your service box.

Why?

  • To upgrade the water system capacity and reliability as part of the Region of Peel’s State of Good Repair program.

When?

  • We expect to start work on or about April 23, 2018 starting at Elmbank Road and Indian Line.
  • The project should be completed before December 2018. All work is under warranty for two years from the completion date.
  • We will start restoring the road when all water system replacements and transfers are complete, and as weather permits.

Who can you call?

Region of Peel Personnel
Contact Responsibilities Phone Number
Scott Durdle Project Manager 905-791-7800 ext. 5052
Lester Bruno Construction Inspector 905-791-7800 ext. 3246
CG Construction Services Ltd.
CG Construction will do the work, under contract to the Region of Peel
Contact Responsibilities Phone Number
Joe Caputo Site Superintendent 416-991-5348
Donny Mele Project Manager 647-884-4345

Working Hours

  • Our contractor’s normal working hours are from 7 a.m. to 7 p.m. These hours are consistent with the local municipality’s bylaws. We understand this may cause some inconvenience, but a shorter working day would mean the project would take longer to complete.

Traffic and Parking Control

  • We may need to reduce traffic to a single lane during construction. If we have to reroute traffic, we will place signs giving directions.
  • No on-street parking will be permitted during working hours 7 a.m. to 7 p.m., Monday to Friday.
  • Do not park or leave unattended vehicles on the road during working hours.

Driveway Access

  • Due to construction activities, we may need to block your driveway for a short time. We will contact you before we do this to arrange for the best time and for alternate access, if needed. If your driveway is blocked, you may choose to park on a side street for a short time. If you need immediate access to your driveway, the contractor will have road plates available to quickly allow access in and out of your driveway.
  • Please call the Project Manager if you have special needs related to access or business hours.

Irrigation or Sprinkler Systems

  • Please tell the inspector if you have underground irrigation or a sprinkler system outside your property line.
  • You may wish to move the sprinkler lines to inside your private property to avoid damage.

Interrupting Your Water Supply

  • It is our goal to let you know 48 hours (2 days) in advance if we need to shut off your water. Occasionally, we may have to reduce this notice to 24 hours.
  • If we have to shut off your water because of an emergency, we will do everything we can to fix the problem as quickly as possible.

Vibrations

  • You may feel slight vibrations from the construction work.

Replacing and Taking Care of Your Sod

  • The contractor will take care of any sod we replace for 30 days.
  • You can help the sod to stay healthy by watering it for one hour in the early morning, two or three times a week. This is especially important in hot or dry weather.
  • We will replace your sod as soon as we can, but there may be a short delay.

Repairing Your Driveway

  • If we need to cut your driveway to replace the existing service valve or access the watermain, we will repair the asphalt in the disturbed area from edge to edge across the driveway. Unfortunately the Region cannot completely replace your driveway.
  • We will repair your driveway as soon as we can, but there may be a short delay.

Repairing the Road, Curbs, and Sidewalks

  • We will start restoring the road and boulevard once all replacements and service transfers are complete and as weather permits.
  • We will complete the restoration on a street-by-street basis.

Project Updates

  • The Region of Peel will always let you know if there are any major changes to the plans.
  • We will try to disturb you as little as possible.
  • Please call the project manager or inspector if you have any concerns or special needs.

Email questions or comments

| Back to Mississauga Construction Projects |

Revised: Wednesday April 18 2018

www.peelregion.ca

Home | Contact Us | Search | A-Z Topic List
Privacy & Terms of Use | Service Commitment

Smaller Text Larger Text